In many kitchen refurbishments, plastering is planned after the necessary first-fix service work and before final kitchen installation and decoration. The exact order depends on the design, wall condition and which surfaces will remain accessible.
Get disruptive service work done first
Electrical and plumbing changes that open or chase walls should normally be coordinated before the final plaster finish. Otherwise newly finished surfaces can be cut into again.
Know where units and splashbacks will go
The plasterer needs to understand the kitchen layout, especially where surfaces disappear behind units or require particular preparation for later finishes. Do not assume every hidden wall needs the same decorative standard.
Protect the finish from the installation stage
Kitchen fitting still involves drilling, fixing and moving large items. Build in sensible protection and allow the plaster to dry before later decorating or finish-sensitive work.
Sequence beats speed
Rushing plastering in before the service layout is final can create more making good. Share the kitchen plan and trade schedule so the wall work supports the project rather than fighting it.
Coordinate first-fix services, then plaster the agreed surfaces before final kitchen fitting wherever practical. Use the actual kitchen plan to set the sequence.